On November 19 at 06:19, an emergency outage occurred on the 500-kV L-503 power transmission line running from the Sirdaryo thermal power plant to the regions of the Fergana Valley and passing through Tajikistan, due to adverse weather conditions. According to the Energy Ministry, preliminary information indicates that one of the line’s support towers collapsed in a rugged, hilly area, triggering the automatic protection system and temporarily halting power transmission along the line. As a result, some consumers experienced supply interruptions, and temporary restrictions will be introduced in certain areas of the valley regions until repair work is completed.

Key Takeaways: An accident occurred at 06:19 on November 19 on the 500-kV L-503 line; a support tower collapsed in difficult terrain on Tajik territory; specialists and emergency repair teams have been deployed; temporary electricity restrictions are expected in parts of the Fergana Valley until repairs are finished.

The incident highlights the vulnerability of energy infrastructure during severe weather, particularly on sections crossing complex terrain and neighboring territory. Because the line passes through Tajikistan, restoration requires coordination with relevant organizations in that country. Specialists and emergency repair brigades have been mobilized under the leadership of Uzbekistan National Electric Networks, and joint rapid-response work is underway with Tajik counterparts to eliminate the consequences and restore the line. This requires assessing the technical condition of the line and safely restoring the collapsed tower.

The Energy Ministry said: “Until repair and restoration work is completed, temporary restrictions will be introduced in the electricity supply to certain areas of the Fergana Valley regions.” Preliminary reports say adverse weather caused a support tower in a rugged hilly area to collapse, activating automatic protection and temporarily stopping transmission along the line, which in turn caused outages for some consumers.

Repair and restoration work is currently continuing at the site, with specialists assessing the line’s technical condition. The next steps include restoring the collapsed tower, re-energizing the line and fully returning electricity to consumers. Authorities are expected to provide further details on repair timelines and affected areas, while residents and businesses are advised to prepare for temporary disruptions. As the process of eliminating the consequences continues, restoring the stability of the power system remains a priority.