The Energiya Coordination and Dispatch Center (KDM), which coordinates electricity flows among Central Asian countries, has launched the selection of a consulting company to design and launch a pilot electricity market involving Uzbekistan, Kazakhstan, Kyrgyzstan and Tajikistan. According to the center’s announcement, applications will be accepted until Nov. 30, and the procurement plan puts the estimated contract value at $2 million. The project is financed under the World Bank’s Regional Electricity Market Interconnectivity and Trade (REMIT) program, which is intended to develop regional power trade and strengthen cross-border grids.
Key Takeaways: The tender was announced by the Energiya KDM, with applications due by Nov. 30 and an estimated contract of about $2 million. The pilot covers Uzbekistan, Kazakhstan, Kyrgyzstan and Tajikistan, with preliminary work scheduled for May 2027 and trading potentially starting in late 2028 or early 2029. The first stage is expected to create a Day-Ahead Market (DAM).
The project’s context is the region’s long-standing need to use available generation more efficiently and to manage seasonal imbalances. Central Asia’s hydropower capacity is concentrated largely in Kyrgyzstan and Tajikistan, while thermal generation remains important in Kazakhstan and Uzbekistan. Periodic surpluses and shortages create room for short-term trade, and REMIT is meant to strengthen the infrastructure and institutional framework for such exchanges. The regional trading platform is not designed to replace existing bilateral agreements but to complement them.
Under the technical specifications, the selected consultant must prepare legal and organizational documents, develop an electronic trading platform, create a pricing and settlement system among participants, and support initial market operations. The system is expected to take about 18 months to develop and implement, after which the contractor must operate it for another two years; the contract includes an option for annual extension. A detailed schedule in the technical specifications envisages that trading will begin about 20 months after the contract is signed, meaning that if initial deadlines are met, the pilot market could start in late 2028 or early 2029.
The first stage is planned as a Day-Ahead Market: participants will be able to submit buy or sell orders for electricity to be delivered during specific hours of the following day. National market requirements will be determined first; approved participants may then offer surplus electricity on the regional platform or place orders to cover shortages. Initial participants are expected to include national energy companies, single buyers of electricity and system operators, while each country will independently decide which organizations are eligible to trade.
Trading is to be conducted in U.S. dollars, with prices planned per megawatt-hour. Settlements will use a zonal model: in each trading zone, prices will be calculated by a special algorithm taking into account demand, supply and grid constraints. The mechanism is expected to help countries use available generation more efficiently and ease short-term power shortages through imports from neighbors. The next steps are to identify the tender winner, finalize the contract and coordinate with national regulators; if the stated timeline holds, the pilot market could be launched in late 2028 or early 2029.
Source: www.gazeta.uz